WhatsApp engineers guide Nepal's desperate search through flood-buried hydropower tunnels

Over 1,200 people killed in the flood; approximately 900 missing from six hydropower plants, with at least 8-46 potentially trapped in tunnel chambers; over 4,000 people still missing overall.
I am surviving on the hope that he will return.
A father waiting for news of his missing son, an environmental engineer buried in the flooded tunnels.
Mark

Why did engineers have a WhatsApp group set up before the flood even happened?

Mimi

They were coordinating work on the hydropower projects themselves—it was a professional tool. When the disaster hit, it became something much larger: a real-time connection between people who knew the tunnel systems and the rescue teams trying to navigate them.

Luke

But how reliable is that knowledge? The flood changed the terrain. The tunnels aren't the same anymore. Are rescuers actually finding people, or are they following maps of places that no longer exist?

Mark

That's a fair point. So what's actually been found so far?

Mimi

No one has been found alive in any of the tunnels yet. But officials believe people might be trapped in sealed chambers with access to supplies. At Rasuwagadhi, they think 46 could be in one chamber. At Chilime, at least eight.

Luke

That's speculation based on where people were last seen, not confirmation. The article doesn't say anyone has actually communicated from inside the tunnels.

Mark

How are rescuers even getting into these tunnels if they're buried under metres of debris?

Mimi

It's slow work. At Upper Trishuli 3A, it took six days just to unbury the entrance. Once they get in, they're using excavators to move boulders and trying to pump oxygen through pipes into cavities.

Luke

And they've reached 250 metres into one tunnel at Rasuwagadhi before hitting a complete blockage. That's real progress, but it also shows how far they still have to go.

Mark

Some people did escape, though.

Mimi

Yes. A civil engineer named Jan Jiwan Thakur got a warning moments before the flood hit and led about 100 people uphill. Another man, Dhan Bahadur Tamang, escaped through a tunnel at the same plant, though he saw bodies on his way out.

Luke

So the tunnels can be a way out—if you know them and if you're there when the flood hits. But that doesn't tell us whether anyone trapped inside now could survive long enough to be found.

  • A glacier collapse sent 2.2 million tonnes of debris crashing through the Trishuli valley, entombing six hydropower plants and erasing nearly 900 workers from contact in a single morning.
  • Rescue teams face tunnels that no longer match any map — mud-choked, structurally altered, their entrances buried under metres of rock and soil, with one team needing six days just to reach a tunnel entrance.
  • A WhatsApp group originally built for project coordination has swelled to 500 members, becoming an emergency nerve center where engineers post schematics, tunnel dimensions, and the phone numbers of the missing within minutes of being asked.
  • At Rasuwagadhi, rescuers pushed 250 metres into a tunnel before hitting a total blockage, yet pressed on — officials believe 46 people may be sheltering in an interior chamber with access to food and water.
  • Oxygen is being pumped through pipes into buried cavities, but as of the latest reports, no survivors have been found inside any of the tunnels, and more than 4,000 people remain missing across Nepal.

In the aftermath of a catastrophic flash flood that swept through Nepal's Trishuli valley on August 26, burying six hydropower plants and swallowing nearly 900 workers into the earth, a quiet digital fellowship of engineers has become the connective tissue between the living and the lost. What began as a professional coordination group on WhatsApp transformed, in the hours after disaster, into a real-time archive of human knowledge pressed into service against the darkness — schematics shared in minutes, tunnel dimensions recalled from memory, names of the missing passed hand to hand through a phone screen. The flood killed more than 1,200 people and erased a tenth of Nepal's power generation capacity, but in the tunnels beneath the debris, the search for survivors continues, guided by those who once built what the mountain has now buried.

On August 26, a glacier collapse sent a wall of water, mud, and rock tearing through Nepal's Trishuli valley, killing more than 1,200 people and burying six hydropower plants — at least three still under construction — beneath 2.2 million tonnes of debris. Around 900 workers from those facilities disappeared. Rescue teams were left with a near-impossible task: searching tunnel networks, now entombed and transformed by the flood, for anyone who might still be alive inside.

Before the disaster, engineers on the hydropower projects had built a WhatsApp group to coordinate their work. Afterward, it became something else entirely. The group expanded to more than 500 members — government officials, military personnel, company staff, and technical experts — exchanging tunnel schematics, structural details, and location data in real time. When a government official asked for layout drawings of the Chilime plant, detailed schematics arrived within minutes. Similar exchanges followed across multiple sites, giving rescuers a navigational thread through infrastructure that no longer resembled its original design.

The conditions were brutal. At Rasuwagadhi, teams pushed 250 metres into one tunnel before hitting a complete blockage, yet continued — officials believed 46 people might be sheltering in an interior chamber. At Upper Trishuli 3A, it took nearly six days just to reach the tunnel entrance. Once there, rescue workers began pumping oxygen through pipes into any cavities where survivors might be waiting.

Some had already escaped. Civil engineer Jan Jiwan Thakur received a warning moments before the flood and led roughly 100 colleagues uphill to safety. Dhan Bahadur Tamang navigated out through a tunnel in total darkness, debris rushing past him, passing bodies on his way to the surface. Others were not so fortunate, and the WhatsApp group became a place where members posted the names and phone numbers of the missing alongside technical drawings — human desperation and engineering knowledge occupying the same thread.

The flood destroyed 10 per cent of Nepal's power generation capacity and left more than 4,000 people missing nationwide. For Rajesh Shrestha, waiting for news of his 30-year-old son Rajish — an environmental engineer at Upper Trishuli 1 — the scale of the catastrophe collapsed into a single doorway he keeps watching. "Whenever I look outside, I imagine seeing him carrying a bag and coming home," he said. Rescue teams continue their work in the tunnels below, guided by engineers typing into their phones in the dark.

On August 26, a wall of water, mud, and rock tore down the Trishuli valley in Nepal, collapsing a glacier and unleashing a flood that killed more than 1,200 people. The deluge buried six hydropower plants—at least three still under construction—under 2.2 million tonnes of debris. About 900 workers from those facilities vanished. In the days that followed, rescue teams faced an almost impossible task: finding anyone who might have survived inside tunnels designed to channel water or provide access to the plants, now entombed beneath rock and soil.

Before the flood struck, engineers working on the hydropower projects had created a WhatsApp group to coordinate their work. After the disaster, that group became something else entirely: a lifeline for rescuers. The chat expanded to more than 500 members—government officials, military personnel, hydropower company staff, and technical experts—all working in real time to guide search teams through tunnel networks that no longer resembled their original design. When a government official typed into the group asking for layout drawings of the Chilime plant, a response came back within minutes: detailed schematics of the powerhouse and access tunnels. Similar exchanges followed as rescuers sought guidance on tunnel locations, dimensions, and structural details that might help them navigate the buried infrastructure.

The challenge was immense. The flood had not simply closed the tunnels; it had transformed them. Mud, rocks, soil, and debris had accumulated inside. Entrances were buried under metres of material. At Rasuwagadhi hydropower plant, rescue workers pushed 250 metres into one tunnel before hitting a complete blockage. Yet they kept trying. Officials believed that 46 people might be trapped in a chamber at that site, possibly with access to food and water. At Upper Trishuli 3A, it took almost six days just to reach the tunnel entrance because it was so thoroughly buried. Once there, rescue teams began trying to pump oxygen through pipes into any cavities where survivors might be sheltering.

Some workers had already escaped by understanding the tunnel systems. Jan Jiwan Thakur, a civil engineer at Upper Trishuli 1, was warned moments before the flood arrived. He and about 100 others from the facility ran uphill and survived. Dhan Bahadur Tamang made it out through a tunnel at the same plant, navigating in darkness as pipes and equipment rushed past him. He saw dead bodies during his subterranean escape. Others were not so fortunate. The Nepal Independent Power Producers' Association reported that at least eight people could be trapped at Chilime. No one had been found alive in any of the tunnels by the time rescue efforts were well underway.

On the WhatsApp group, members posted names and phone numbers of missing workers, asking government officials to pass them to telecom authorities in hopes of locating their last recorded positions. The group became a repository of technical knowledge and human desperation at once. A manager at the Nepal Electricity Authority, speaking anonymously, confirmed that rescue workers had asked former plant employees for advice about tunnel layouts through the chat. The drawings shared there had proven useful.

The flood wiped out 10 per cent of Nepal's entire power generation capacity. More than 4,000 people remained missing across the country. But for the families of the 900 missing from the hydropower plants, the focus was narrower and more intimate. Rajesh Shrestha, who runs a workshop making window grills, waited for news of his 30-year-old son, Rajish, an environmental engineer at Upper Trishuli 1. "Whenever I look outside, I imagine seeing him carrying a bag and coming home, just as he used to," Shrestha said. "I am surviving on the hope that he will return." Rescue teams continued their work in the tunnels, guided by engineers typing coordinates and advice into their phones, searching for anyone who might still be alive in the darkness below.

The flood has altered the terrain around the tunnels and changed their structure, while mud, rocks, soil and other debris had accumulated inside. This is not a normal closure of tunnels.
— Raja Ram Basnet, Nepal army spokesperson
We just ran away towards the hillside and, after two to three minutes, when we looked down, everything was gone. The flood debris had entirely covered our office area.
— Jan Jiwan Thakur, civil engineer at Upper Trishuli 1
Want the full story? Read the original at CNA ↗